CX-009791: Categorical Exclusion Determination

Blast and Paint West Hackberry, Texas 22 Header Piping CX(s) Applied: B1.3 Date: 01/23/2013 Location(s): Louisiana Offices(s): Strategic Petroleum Reserve Field Office

Office of NEPA Policy and Compliance

January 23, 2013
Estimated Read Time   min
Blast and Paint West Hackberry, Texas 22 Header Piping
CX(s) Applied: B1.3
Date: 01/23/2013
Location(s): Louisiana
Offices(s): Strategic Petroleum Reserve Field Office

Subcontractor shall provide all transportation, materials, equipment, supplies, tools, facilities, utilities, labor and supervision required to blast and paint the West Hackberry, Texas 22 header piping. The header piping to be painted begins on the westward side of this piping system, located at the 4 valve manifold, and ends before the road located on the east side of the facility. All ground penetrations through the earth surface will be excavated and rewrapped.