Curecanti-Crystal 115 Kilovolt Transmission Line Routine Maintenance of Existing Access Roads and Right-of-Ways CX(s) Applied: B1.3 Date: 08/07/2012 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region
Office of NEPA Policy and Compliance
August 7, 2012Curecanti-Crystal 115 Kilovolt Transmission Line Routine Maintenance of Existing Access Roads and Right-of-Ways
CX(s) Applied: B1.3
Date: 08/07/2012
Location(s): Colorado
Offices(s): Western Area Power Administration-Rocky Mountain Region
Western Area Power Administration (Western) proposes to perform routine maintenance of existing access roads and right-of-ways (ROW) along the Curecanti-Crystal (CCI-CRY) 115-kilovolt (kV) transmission line to safely access structures 112,1/6,4/1, 6IS-6, 7/1-9, and 8/1-4 (approximately 3 miles). The project is located on private and U.S.. Bureau of Land Management (BLM) lands in Montrose County, Colorado.
CX(s) Applied: B1.3
Date: 08/07/2012
Location(s): Colorado
Offices(s): Western Area Power Administration-Rocky Mountain Region
Western Area Power Administration (Western) proposes to perform routine maintenance of existing access roads and right-of-ways (ROW) along the Curecanti-Crystal (CCI-CRY) 115-kilovolt (kV) transmission line to safely access structures 112,1/6,4/1, 6IS-6, 7/1-9, and 8/1-4 (approximately 3 miles). The project is located on private and U.S.. Bureau of Land Management (BLM) lands in Montrose County, Colorado.