Wood Pole Replacements As Needed on the Shelton-Fairmount No. 1, 115 Kilovolt Transmission Line CX(s) Applied: B1.3 Date: 05/24/2012 Location(s): Washington, Washington Offices(s): Bonneville Power Administration

Office of NEPA Policy and Compliance

May 24, 2012
Estimated Read Time   min
Wood Pole Replacements As Needed on the Shelton-Fairmount No. 1, 115 Kilovolt Transmission Line
CX(s) Applied: B1.3
Date: 05/24/2012
Location(s): Washington, Washington
Offices(s): Bonneville Power Administration

Bonneville Power Administration proposes to replace deteriorating wood poles and associated structural/electrical components (e.g. crossarms, insulators, and guy anchors) at existing H-frame structures along the subject transmission line in Mason and Jefferson counties, Washington.