Replacement of A-Area Critical Fire Hydrants 3001, 3013, 3018, & 3032 CX(s) Applied: B1.3 Date: 05/07/2012 Location(s): South Carolina Offices(s): Savannah River Operations Office
Office of NEPA Policy and Compliance
May 7, 2012Replacement of A-Area Critical Fire Hydrants 3001, 3013, 3018, & 3032
CX(s) Applied: B1.3
Date: 05/07/2012
Location(s): South Carolina
Offices(s): Savannah River Operations Office
The attached scope of work describes the installation of a new 6 inch resilient seat curb box gate valves and the replacement of existing fire hydrants connected to the outside underground (OSUG) fire water system in the A-Area.
CX(s) Applied: B1.3
Date: 05/07/2012
Location(s): South Carolina
Offices(s): Savannah River Operations Office
The attached scope of work describes the installation of a new 6 inch resilient seat curb box gate valves and the replacement of existing fire hydrants connected to the outside underground (OSUG) fire water system in the A-Area.