Record of Categorical Exclusion for Bryan Mound Building BE-2 Drainage Improvements and Foundation Repair CX(s) Applied: B1.3 Date: 11/16/2011 Location(s): Texas Offices(s): Strategic Petroleum Reserve Field Office
Office of NEPA Policy and Compliance
November 16, 2011Record of Categorical Exclusion for Bryan Mound Building BE-2 Drainage Improvements and Foundation Repair
CX(s) Applied: B1.3
Date: 11/16/2011
Location(s): Texas
Offices(s): Strategic Petroleum Reserve Field Office
Subcontractor shall furnish all labor, materials, equipment, tools, transportation, supervision, mobile lifting equipment, and rigging required to repair timber piles which support Bryan Mound Building BE-2. Subcontractor shall modify the ground surface around the building with crushed stone to prevent soil washout and improve drainage conditions which led to disrepair of the building foundation.