CX-007076: Categorical Exclusion Determination

Install New Power Poles in A & B AreasCX(s) Applied: B1.3Date: 08/22/2011Location(s): Aiken, South CarolinaOffice(s): Environmental Management, Savannah River Operations Office

Office of NEPA Policy and Compliance

August 22, 2011
Estimated Read Time   min
Install New Power Poles in A & B Areas
CX(s) Applied: B1.3
Date: 08/22/2011
Location(s): Aiken, South Carolina
Office(s): Environmental Management, Savannah River Operations Office

This job relocates two sets of 200A voltage regulators that are no longer required on the L-P 13.8 kilovolt line. They will be platform installed at two locations on the 13.8 kilovolt feeder 01 that ties A and B Areas.