North Oakes Tap of the Edgeley to Forman 69 Kilovolt line
CX(s) Applied: B4.11
Date: 06/08/2011
Location(s): North Dakota
Office(s): Western Area Power Administration-Upper Great Plains Region

Central Power Electric Cooperative is proposing to tap into the Western Area Power Administration (Western) Edgeley to Forman 69 kilovolt transmission line with a new substation to meet load growth in the Southeastern North Dakota area.