Life Cycle of Photovoltaic Systems: Procure a New Photovoltaic System

Banner Color
Light Text on a Dark Overlay (Default)

If agencies expect a 30-year lifetime for their photovoltaic (PV) system, it is important to ensure the system is well maintained and designed with safety in mind.

Specifications in design and equipment during the procurement process can help prevent vulnerabilities and support the development of a long-lasting system.

This page outlines key considerations to assist with procuring PV systems. Resources are provided for a deeper dive into the topics below. Return to the Life Cycle of PV Systems landing page to explore more phases in this process.

ON THIS PAGE:

Did You Know?

PV systems are highly reliable. A 2020 report PV Field Reliability Status—Analysis of 100,000 Solar Systems analyzed more than 100,000 solar PV systems and found that 80%-90% of systems performed within 10% of expected performance. Many early-life hardware issues were preventable with proper training and standards.

Perform Project Validation

One of the first steps in procuring a new PV system is validating that no aspects of the site or system render the project infeasible. The screening process, known as project validation, includes three phases: pre-screening, site screening, and financial and regulatory screening. These phases are outlined below. Tools and resources that can assist with project validation are listed under Key Resources.

  • Goal: Determine site-specific metrics, such as solar potential and available space.

    • Ensure project compatibility with future site plans of the agency or developer.
    • Review the electricity supply contract.
    • Determine contract end date, electricity price, procurement plans, departing load penalties, and restrictions that may impact project feasibility.
    • Review and complete agency approval requirements.
    • Review and complete land or building requirements.
    • Identify any fatal issues that would make the site ineligible.
      • Example: A parking lot may not be suitable for a carport system if there is too much truck traffic.
  • Goal: Determine estimated energy consumption, energy demand, specifications unique to the system type (e.g., rooftop or ground-mount), site-specific hazards (e.g., weather), site access, and electrical considerations.

    • Determine PV system size.
      • System size is based on available land/rooftop space, land ownership, parcel size, weather, energy demand, PV production, site topology, land slope, and existing renewable energy resources at the site.
    • Consider construction logistics and requirements.
      • These include construction and operating permits, stormwater management requirements, erosion control measurements, soil type, water drainage, and sediment control measurements.
    • Determine site access (e.g., roads).
    • Check for module glare requirements, particularly near airports.
    • Get approvals from site tenants and neighbors.
    • If in a competitive electricity market, review the site’s electricity contract.
    • Review zoning rules, land use regulations, ADA/fire lane requirements (e.g., carports), and shipping access.
      • Additional checks for carport include reviewing access with the fire marshal, planning to add protective bollards for collision prevention of large vehicles, and designing for the expected height of vehicles.
    • Consult with the site’s utility about interconnection and electrical infrastructure needs.
      • These include whether the project has adequate interconnection capacity, whether the site is on a network distribution system, interconnection options, whether new electrical lines must be built to accommodate interconnection (ground-mounted), site-specific electrical requirements/upgrades, whether a system integration study is needed, acceptable inverter locations and enclosures, and whether the solar project will provide security or resilience benefits or be “microgrid ready.”
  • Goal: Determine policy and regulatory considerations, utility rates, capital and operation and maintenance (O&M) costs, incentives, life cycle costs, state regulations, and utility policies.

    • Review market, state, and utility regulations.
      • Regulations may focus on PV system sizing, power purchase agreement legality, interconnection rules, utility policies such as net metering, power pricing, etc. to ensure that project aligns with local, agency, and/or other relevant requirements.
    • Analyze project economics. To conduct a financial analysis for the PV system:
      • Review electricity rate tariff information and net metering policy.
      • Research incentives.
      • Research Solar Renewable Energy Certificate (SREC) markets to find out whether SRECs are valuable.
      • Consider whether there is existing electrical infrastructure capacity that may be used.
    • Using the information in the steps above, conduct a project cost analysis.
    • Determine whether the National Historic Preservation Act applies.
    • Complete an environmental assessment to comply with the National Environmental Policy Act or obtain a categorical exclusion for certain rooftop systems.
      • Environmental constraints may relate to endangered flora and fauna at site, pollinator habitat, or riparian areas.
    • Coordinate with local utility on tariffs, incentives, and interconnection requirements. Questions for the utility may include:
      • What incentives and policies are available for my project? Are net metering and feed-in tariffs available? What about virtual net metering or community renewables?
      • What is the allowable renewable energy project size? How do you measure project capacity (in DC or AC)?
      • How will the project impact my utility costs? Will standby charges be used? Will my current tariff change?
      • Is there a template interconnection agreement? Who will need to sign this?
    • Consider the project site agreement, i.e., the contract that gives a developer permission to use the site to install and/or operate a PV system.
  • Screening tools/databases:

    Project validation tools for installing systems on previously contaminated infrastructure (i.e., brownfields/landfills):

    Other resources:

Identify Weather Risks

Weather Risk Awareness and Assessment

When siting a PV system, agencies should assess weather risks and take appropriate design measures. Although some design elements may increase upfront costs, they can reduce O&M costs and system failures over time.

Actionable Steps

  • Assess the site's vulnerability using the Federal Emergency Management Agency’s (FEMA’s) National Risk Index, and design against expected risks. For example:
    • Elevate critical equipment above 100-year flood levels.
    • Require foundation specifications for wet soil conditions (for ground-mounted systems).
    • Incorporate site-related stormwater mitigation design measures, such as establishing pollinators and native plants that absorb stormwater (for ground-mounted systems).
    • For wildfire-prone areas, manage vegetation surrounding the PV system. For example, co-siting PV with native vegetation may be associated with reduced wildfire risk, reduced installation and operational costs, and environmental benefits. For rooftop systems, install modules at least one foot above the surface of the roof when possible.
    • For high-wind areas, ensure that site topography is appropriate and prevents damage risks.
  • Include technical specifications for weather hazard protection in solicitation and contracts.

Identify Technical Specifications

Technical specifications or “tech specs” outline the technical requirements for system procurement and installation. These specifications should be reflected throughout the project life cycle including:

  • Contractor award and selection criteria
  • Procurement documents
  • Design drawings and diagrams
  • Submittal reviews
  • Site mobilization and equipment delivery
  • Commissioning review and verification.

This is summarized in the flow diagram below.

Technical Specifications flow diagram showing the Bid-RFP steps, Contract steps, Design Process steps, Mobilization steps, and Commission steps.

Prepare an Operations and Maintenance Plan

Preparing an O&M plan during system design helps reduce vulnerabilities and improve performance. Benefits of an O&M plan include: 

  • Increased system performance and decreased downtime
  • Extended lifespan
  • Improved safety and reduced safety risks.

Prerequisite considerations to draft a successful O&M plan include equipment management and third-party coordination.

Equipment Management

  • Select low- or no-maintenance alternatives and equipment with lower failure rates when available (for example, plastic wire ties may require early replacement whereas metal ones may not).
  • Make use of connected inverters for remote testing, software configurations and/or updates, and remote resets.
  • Provide required access to and clearance around equipment for maintenance.
  • Apply the latest version of IEC 62446: Grid Connected Photovoltaic Systems-Minimum Requirements for System Documentation, Commissioning Tests, and Inspections, which requires documentation of the system, array testing, and whole-system performance testing (applicable to commercial, industrial, and field systems). 

Third-Party Coordination

Developing an O&M Plan organization chart with two main branches: Self-perform O&M and Standard O&M Contract, with branches below this: Full and open, General services administration (GSA) supply schedules, and Add to a master maintenance contract

Enable third-party inspections of engineering, procurement, and construction installations to spot operational problems before acceptance.

Options to pursue for O&M for a new PV system include self-performing O&M and pursuing a standard O&M contract. A standard O&M contract includes several options, which are displayed below.

Type of O&M PlanStandard ContractWho This Is ForSteps to Take
Self-Perform O&MN/AAgencies seeking to perform their own O&M. Usually larger facilities with existing maintenance programs.Consider enrolling staff in a training course. Also consider the availability of spare parts.
Full and OpenYAgencies seeking a contract awarded through a competitive bidding process due to unique or complex requirements, or if GSA Schedule contractors are not available in the area.Refer to the Request for Proposal (RFP) Template for Government-Owned Solar PV Systems to create an O&M plan.
General Services Administration (GSA) Supply SchedulesYAgencies seeking a contract with pre-negotiated terms and pricing for ease of procurement, vetted contractors, or to satisfy requirements such as small or women-owned businesses.Refer to information at GSA.gov, namely Operations and Maintenance Services of Government-Owned Solar PV Systems to create an O&M plan.
Adding to a Master Maintenance ContractYAgencies with an existing contract in place.Most straightforward, add onto existing contract with items relevant to a new system (e.g., through analyzing balance-of-system efficiency and other system descriptors).

PV System Life Cycle

You're on phase 1 of the PV System Life Cycle. Learn more about each phase and explore key resources: