
A large office complex that served as a hub for Hanford cleanup efforts for more than 20 years has been torn down as part of the site's ongoing risk-reduction work. July 1, 2025

Office of Environmental Management Principal Deputy Assistant Secretary Roger Jarrell recently joined community stakeholders and employees at the West Valley Demonstration Project to celebrate a major milestone. June 24, 2025.

Idaho Cleanup Project crews have completed demolition of the Submarine 1st Generation Westinghouse naval reactor prototype plant, safely using explosives to carry out this key milestone. June 3, 2025

The Oak Ridge Office of Environmental Management and contractor UCOR are conducting the largest demolition to date at the Y-12 National Security Complex — teardown of the Alpha-2 building. June 3, 2025
Demolition is underway on the last remaining hot cell structure at the former Radioisotope Development Laboratory at Oak Ridge National Laboratory — a U.S. Department of Energy Office of Environmental Management priority for 2025.

Idaho Cleanup Project crews have achieved a significant milestone in the deactivation and demolition of the defueled Submarine 1st Generation Westinghouse naval nuclear propulsion prototype reactor plant,

Cleanup crews recently removed the first transite panel from X-333 to prepare for the demolition of the second of three former uranium enrichment process buildings at the Portsmouth Site.
Crews with the Oak Ridge Office of Environmental Management and contractor UCOR make headway preparing for the next major demolition project at the Y-12 National Security Complex.

The U.S. Department of Energy (DOE) Oak Ridge Office of Environmental Management (OREM) notched a significant cleanup achievement after crews finished characterizing all 21 hot cells at a Cold War facility.

The Idaho Cleanup Project has logged a series of performance and cost efficiency victories, allowing it to reinvest associated savings into more cleanup work.