DOE-Savannah River, the South Carolina Department of Health and Environmental Control and U.S. Environmental Protection Agency have signed an updated Savannah River Site (SRS) Liquid Waste Program milestone agreement incorporated in the SRS Federal Facility Agreement.

DOE-Savannah River, the South Carolina Department of Health and Environmental Control and U.S. Environmental Protection Agency have signed an updated Savannah River Site (SRS) Liquid Waste Program milestone agreement incorporated in the SRS Federal Facility Agreement.

AIKEN, S.C.EM’s field office at the Savannah River Site (SRS), in partnership with state and federal regulators, has finalized a high-level waste tank milestones agreement guiding the work to clean up one of the largest environmental risks in South Carolina.

Over the last several months, DOE-Savannah River (DOE-SR), the South Carolina Department of Health and Environmental Control (DHEC) and U.S. Environmental Protection Agency (EPA) have reviewed, negotiated and agreed to revisions to the SRS Federal Facility Agreement (FFA). The FFA establishes a procedural framework and directs comprehensive remediation at SRS, including high-level waste tank milestone agreements and other site cleanup priorities.

The revision to the FFA outlines the schedule for waste removal and operational closure of the 16 oldest-style tanks at SRS. All 43 remaining tanks are slated to be operationally closed by 2037.

The radioactive liquid waste stored at SRS was generated as a byproduct from the processing of nuclear materials for national defense, research, medical programs and outer space missions. Totaling about 34 million gallons, the waste is stored in underground carbon-steel waste tanks grouped into two tank farms at SRS.

Revising the FFA and the waste tank milestone commitments ensures regulatory requirements align to allow EM’s liquid waste facilities to operate as efficiently and effectively as possible, according to Jim Folk, DOE-SR’s assistant manager for waste disposition.

“The No. 1 goal agreed upon by all parties is to reduce risk to the environment by removing waste and closing tanks,” Folk said. “DOE will continue its ongoing positive relationship with our regulators by involving DHEC and EPA throughout each stage of the waste removal process to explain the activities undertaken, results of removal operations, challenges and next steps.”

EM’s liquid waste contractor at SRS, Savannah River Mission Completion (SRMC), assisted with FFA milestone negotiations. For the first time, a single contractor now has responsibility for all the liquid waste processing facilities at SRS, which is a significant benefit to completing the liquid waste mission, according to SRMC President and Program Manager Dave Olson.

“Having the milestones set today allows us to focus on delivering results and executing the work that will drive our mission to completion,” Olson said. “With many facility improvements and process optimizations in place and being implemented, SRMC plans to aggressively pursue early success to meet the FFA milestones.”

Henry Porter, DHEC’s chief of the Bureau of Land and Waste Management, signed the agreement on behalf of the environmental regulator.

“The South Carolina Department of Health and Environmental Control considers the high-level waste at the Savannah River Site one of the largest environmental risks in the state,” Porter said. “Collaborating with the federal government to agree upon these milestones, values and goals is critical in achieving the site’s waste cleanup mission and protecting the community and environment beyond the barricades.”

Randall Chaffins, EPA’s Region 4 acting director for the Superfund and Emergency Management Division, described the importance of partnering with DOE and DHEC to ensure accountability.

“Safely remediating the radioactive liquid waste and removing the tanks from service at the Savannah River Site protects human health and the environment,” Chaffins said. “EPA is appreciative of the mutually beneficial partnership with DOE and its contractors.”