Bonneville Power Administration (BPA) proposes to install new media converters, fiber, and appurtenances at the patch panel inside of BPA's existin…
Doniphan Electric Cooperative will completely rebuild the Blair substation. A full project narrative is also attached, which provides additional de…
Bonneville Power Administration (BPA) proposes to have BPA-owned substation equipment removed from Nevada (NV) Energy's Winnemucca Substation in Hu…
The project will involve replacing existing expulsion fuses and arresters with non-expulsion types on power lines to reduce wildfire risk, conducti…
The projects will require clearing and grubbing of forested areas totaling approximately 1-2 acres followed by grading to construct a 1 MW Battery …
East River Electric Power Cooperative (ERC) is upgrading the Arlington Tap facility on the WAPA Watertown - Brookings 115 kV transmission line. WAP…
WAPA would acquire additional land around Wessington Springs Substation to mitigate erosion from the substation and minimize damages from neighbori…
Sub-recipient will Install electric grid fault and line sensors, reclosers and telecommunication equipment, replace distribution poles with composi…
This is a targeted, reliability and resiliency improvement driven project at the Leesburg Electric North Substation for the replacement of an out o…
The project involves removal of approximately 6,900 feet of overhead electrical distribution lines, replacement of 4 platform structures and pad-mo…