Grid and Transmission Program Conductor

The Grid and Transmission Program Conductor acts as a clearinghouse for GDO’s transmission and grid resilience financing programs, as well as other existing DOE transmission and grid programs.

For funding opportunities, any content within this website that appears discrepant from a Funding Opportunity Announcement or Request from Proposal is superseded by the FOA or RFP language.

green line

 

Use this tool to find the best program for you:

green line

Programs Summary

ProvisionSummaryEligible EntitiesEligible ProjectsFunding
Transmission Programs    
Transmission Facilitation ProgramProgram that will provide Federal support to overcome the financial hurdles in the development of large-scale new transmission lines, upgrading of existing transmission, and the connection of microgrids in select States and U.S. Territories

May include but not limited to:

  • Transmission developers
  • Microgrid developers

To qualify, projects must meet at least one of the following criteria:

  • New corridor: 1,000 MW or more
  • Existing corridor: Upgrade or new line -- 500 MW or more
  • Microgrid: Project connects an isolated microgrid to an existing transmission, transportation, or telecommunications infrastructure corridor located in Alaska, Hawaii, or a U.S. Territory

$2.5 billion in borrowing authority

Revolving fund

Three types of financing:

  • Capacity contracts
  • Public private partnerships
  • Loans
Transmission Facility Financing ProgramDirect loan program for facility financing

Limited to:

  • Non-federal borrowers
To qualify, projects must be designated by the Secretary to be necessary in the national interest under section 216(a) of the Federal Power Act.$2 billion in borrowing authority
Transmission Siting and Economic Development (TSED) Grant Program

Grant program to support:  

  1. activities carried out by Tribal, state, or local siting authorities to strengthen and accelerate processes for the siting and permitting of electric transmission lines, and
  2. economic development activities in communities that may be impacted by the construction and operation of interstate and offshore transmission lines.    

For siting and permitting activities: siting authorities, defined as Tribal, state, or local governmental entities with the authority to make a final determination regarding the siting, permitting, or regulatory status of a “covered transmission project.”  

 

For economic development activities: siting authorities or any Tribal, state, or local governmental entity proposing to undertake a project in a community impacted by the construction or operation of a “covered transmission project.” 

Examples of siting and permitting activities and economic development activities can be found on Frequently Asked Questions on the Transmission Siting and Economic Development Grant Program.$760 million
Grid Infrastructure Modernization & Improvement Programs    
Grid Resilience State and Tribal Formula Grants ProgramFormula grant program to strengthen and modernize America’s power grid against wildfires, extreme weather, and other natural disasters that are exacerbated by the climate crisis

Limited to:

  • States
  • Territories
  • Tribes

To qualify, grantees must address at least one of the following:

  • Weatherization technologies and equipment
  • Fire-resistant technologies and fire prevention systems
  • Monitoring and control technologies
  • Undergrounding of electrical equipment
  • Utility pole management
  • Relocation of power lines or the reconductoring of power lines with low sag, advanced conductors
  • Vegetation and fuel load management
  • Use or construction of distributed energy resources for enhancing system adaptive capacity during disruptive events, including— microgrids and battery storage subcomponents
  • Adaptive protection technologies
  • Advanced modeling technologies
  • Hardening of power lines, facilities, substations, of other systems
  • Replacement of old overhead conductors and underground cables

$2.3 billion

15% cost share from State, Territory, Tribal grantee

Grid Resilience Utility and Industry GrantsGrants to grid operators for investments to reduce the likelihood and consequences of disruptive events to communities and reduce risk of power lines causing wildfires

May include but not limited to:

  • Electric grid operators
  • Electricity storage operators
  • Electricity generators
  • Transmission owners or operators
  • Distribution providers
  • Fuel suppliers
Same as listed above for Grid Resilience State and Tribal Formula Grants Program.

$2.5 billion

Second round includes FY24 & FY25 together (up to $918 million)

At least 50% cost share from grantee

Smart Grid GrantsGrants to support the deployment of technologies to enhance grid flexibility

Limited to:

  • Institutions of higher education
  • For-profit entities
  • Non-profit entities
  • State and local governmental entities
  • Tribal Nations

To qualify, investments may include:

  • Appliances, specialized industrial and commercial equipment, and transmission and distribution equipment
  • Metering, control, and other devices, sensors, and software
  • Equipment allowing smart grid functions to be operated and combined or coordinated among multiple electric utilities and regions
  • Monitoring, controlling, and integrating distributed generation into grid operations
  • Expanding communications/ broadband technologies to support smart grid activities
  • Integrating electric or hybrid-electric vehicles onto the grid

$3 billion

Second round includes FY24 & FY25 together (up to $1.08 billion)

At least 50% cost share from grantee

Grid Innovation Program

Financial assistance to governmental entities to coordinate and collaborate with electric sector owners and operators to:

  • Demonstrate innovative approaches to transmission, storage, and distribution infrastructure to harden and enhance resilience and reliability and
  • Demonstrate new approaches to enhance regional grid resilience, implemented through states by public and rural electric cooperative entities on a cost-shared basis

Limited to:

  • State
  • Combination of States
  • Tribes
  • Local governments
  • Public Utility Commissions (PUCs)

To qualify, projects must meet at least one of the following criteria:

  • Transmission capacity enhancements
  • Advanced distribution grid assets and functionality including storage
  • Combined systems demonstrating innovative approaches

$5 billion

Second round includes FY24 & FY25 together (up to $1.82 billion)

At least 50% cost share from grantee

If you have questions about GDO’s Transmission planning work, please visit our Enhanced Transmission Planning webpage and if you have additional questions, please reach out to us at Transmission@hq.doe.gov and we will get back to you as quickly as possible.