The Klickitat PUD will upgrade approximately 8,500 feet of old, outdated single phase distribution line to three phase line. These upgrades include…
Distribution Line Hardening, Pole Replacement, Fuse Replacement, Relay Replacement, Substation Upgrades.…
The project includes adding an automatic transfer switch that is rated 15kv and 600 amps.…
The primary scope of this project involves upgrading obsolete electromechanical equipment (circuit breakers, relays, and regulator controls) within…
Install 6 new 69kV transmission breakers, multiple disconnecting switches, and protection relays. …
BPA proposes to allow T-Mobile to upgrade its telecommunications equipment located at structure 20/1 on the Monroe-Novelty Hill No. 1 Transmission …
The Marana Upgrade Project (Project) is proposed by Arizona Electric Power Cooperative (AEPCO) to rebuild the existing Marana Substation within the…
The project focuses on enhancing grid resilience through infrastructure upgrades, including hardening critical facilities, integrating and improvin…
BPA proposes to allow T-Mobile to upgrade the existing wireless antennas located on structure20/1 of BPA's Monroe-Novelty Hill No. 1 transmission l…
Troy Power and Light plans to replace old electric meters with new smart meters, attaching repeaters to existing power poles to establish a network…