RICHLAND, Wash. – Progress toward demolition at the Plutonium Finishing Plant (PFP) on the Hanford Site continued with the safe demolition of a small building near the main PFP complex this month.

Office of Management

June 15, 2016
minute read time
June 2016 PFP 225-WC Demo (6)_700 pixels.jpg
June 2016 PFP 225-WC Demo (9)_700 pixels.jpg

RICHLAND, Wash. – Progress toward demolition at the Plutonium Finishing Plant (PFP) on the Hanford Site continued with the safe demolition of a small building near the main PFP complex this month. The building once housed testing equipment for water effluent that came from PFP. Overall, 92 buildings made up the PFP complex, and about 24 remain. EM and contractor CH2M HILL Plateau Remediation Company are working to safely prepare the remaining buildings for demolition, including the four main processing buildings, which involves some of the most hazardous work at the site