Coordinated Interagency Transmission Authorizations and Permits Program

Expanding electric transmission capacity in the United States is essential to meet growing demand for electricity. The Coordinated Interagency Transmission Authorizations and Permits (CITAP) Program will make the federal permitting process for transmission infrastructure more efficient and effective without sacrificing the quality of environmental reviews. The program establishes the U.S. Department of Energy (DOE) as the lead agency to coordinate and accelerate federal environmental reviews and permitting processes for qualifying electric transmission facilities. 

CITAP Online Portal

To facilitate communication and coordination, the Grid Deployment Office (GDO) has launched the CITAP online portal, a one-stop-shop for qualified transmission developers to track the status of their application, submit materials, and facilitate communication with DOE and other federal agencies. The secure, online portal will be used to share information that will inform Federal permitting agencies’ authorization decisions and enhance transparency.

Why is the CITAP Program important?

New electric transmission capacity in the United States is needed to ensure Americans have access to reliable, affordable, and clean energy. On average, Federal permitting for a new electric transmission line takes approximately four years. Many factors can contribute to lengthy transmission development timelines, such as prolonged and fractured planning processes, difficulty securing financing, and the need to navigate complex environmental permitting processes. 

By enabling the United States to expand transmission capacity at a faster rate and streamlining the federal permitting process, the CITAP Program will help:

How does the CITAP Program work?

DOE released a final rule that will significantly streamline Federal environmental reviews and permitting processes for qualifying onshore electric transmission facilities, while ensuring meaningful engagement with Tribes, local communities, and other stakeholders.

An infographic that has a transmission developer who initaties the pre-application process with the U.S. Department of Energy (DOE). Nine federal agencies coordinate with DOE coordinating agency reviews. The average time to site and permit a transmission project is almost cut in half with a new two-year deadline, four years as the average, and 11 years as the estimated time.

*Relevant federal agencies could include: Department of Agriculture (USDA), Department of Commerce (DOC), Department of Defense (DOD), Department of the Interior (DOI), Environmental Protection Agency (EPA), Federal Permitting Improvement Steering Council (Permitting Council), Council on Environmental Quality (CEQ), and the Office of Management and Budget (OMB)

**Contextualizing electric transmission permitting: data from 2010 to 2020, Niskanen Center, 2024

Background and Standard Schedule

On April 25, 2024, the DOE announced a final transmission permitting reform rule that will streamline the transmission authorization process to a two-year timeline without sacrificing environmental reviews. By improving Federal transmission permitting processes and investing in transmission build out and grid upgrades, DOE is deploying a multifaceted approach to ensuring that Americans have clean, reliable, and affordable power when and where they need it.

A table template for the CITAP standard schedule showing the authorizations, NEPA, NHPA sec 106, RHA sec 10/CWA sec 404 and ESA permitting taking 24 months from issuing Notice of Intent
While the standard schedule is a template, each project may have its own project-specific schedule depending on its scope and location.