There are four major measurement and verification (M&V) activities in the federal energy savings performance contract (ESPC) process. They include:

  1. Determining baselines and estimated savings
  2. Developing the M&V plan
  3. Developing the post-installation M&V report, which is part of conducting post-installation M&V activities
  4. Performing annual M&V, which is part of the conducting annual M&V activities.

 