DOE Distributed Energy Resource Interconnection Roadmap

Banner Color
Light Text on a Dark Overlay (Default)
Photo of distributed wind and rooftop solar.
Rooftop solar and distributed wind systems at CROPP Cooperative in Monroe, WI
David Nevala

The Distributed Energy Resource Interconnection Roadmap identifies solutions to interconnection challenges on the distribution and sub-transmission grids. The roadmap was produced by the U.S. Department of Energy (DOE) Interconnection Innovation e-Xchange (i2X), led by the Integrated Energy Systems Office (IESO). It provides stakeholders with strategies to improve interconnection processes to meet growing demand for more generators, storage systems, large loads, and hybrid facilities on distribution networks.

The U.S. electricity system is changing rapidly as homes and commercial buildings electrify, manufacturing hubs expand, and energy-intensive sectors, such as artificial intelligence (AI) and data centers, continue to grow.   Distributed energy projects play an important role in this change because they offer faster integration, closer proximity to loads, and flexibility in balancing loads. However, interconnection processes must accommodate a growing volume of interconnection requests and adapt to local markets with specific needs.

The roadmap is organized around four goals, each critical to the overall mission of i2X : to enable a simple, fast, and affordable interconnection while enhancing the reliability and security of our electric grid. Developed through extensive stakeholder engagement, the roadmap outlines specific actions that each stakeholder group can take to improve interconnection. The solutions are categorized by time scale and deployment level to help stakeholders identify those that best meet regional needs.

This roadmap serves as a companion to the DOE Transmission Interconnection Roadmap, published in April 2024, which identifies solutions to address current challenges in transmission system interconnection.

DER Interconnection Roadmap Goals

Measurable Targets for Interconnection Reform

This roadmap includes five target metrics for 2030 that can be measured using publicly available data:

  • Decreasing median time from distributed energy project interconnection request to interconnection agreement to: 
    • Less than one day for small systems (< 50 kilowatts (kW))
    • Less than 75 days for medium systems (50 kW – 5 megawatts (MW))
    • Less than 140 days for large systems (> 5 MW)
  • Increasing completion rate from entering the interconnection queue to executing the interconnection agreement to: 
    • > 99% for small systems (< 50 kW)
    • > 90% for medium systems (50 kW – 5 MW)
    • > 85% for large systems (> 5 MW)
  • Ensuring all 50 U.S. States, Washington, D.C., and all U.S. territories have public, detailed, and current interconnection queue data
  • Ensuring zero disturbance events on the bulk power system exacerbated by inaccurate distributed energy project modeling
  • Decreasing the time to restore service after a power outage by 25% (measured by the Customer Average Interruption Duration Index (CAIDI))