This revision adds new poles at CITRC on circuit 54. Poles will be: 54-26A-1, 54-9-4-3 and 54-9-4-4.…
This revision adds scope to revision 1 of the environmental checklist (EC). Power Management has identified additional power poles that need to be …
Design, manufacture & install on an electrical grid a 60 MVA flexible large power transformer (LPT). Also, R&D to improve protective relays and dis…
A survey of the 500kV Monroe-Custer No. 1 transmission line resulted in the identification of a Snohomish County PUD (SCPUD) distribution line that…
BPA proposes to remove the outdated control house at Maupin Substation to accommodate additional equipment to meet future needs. Equipment used to …
The Bonneville Power Administration (BPA) proposes to install a new Power Control Assembly (PCA) building and to remove the existing control house …
The proposed action upgrades power to meet for experiment usage at the Energy Systems Laboratory (ESL). The proposal adds 1.5 megawatts of electric…
The Power Management organization at Idaho National Laboratory needs to perform maintenance and inspection activities on power poles and structures…
Western Area Power Administration (WAPA), Rocky Mountain Region (RMR), conducts routine maintenance activities at existing facilities in five stat…
The Western Area Power Administration is proposing to remove an existing capacitor bank, install new gas breakers, shunt reactors, foundations and …