In-kind replacement of existing overhead top of pole electric cable, utilizing the majority of existing utility poles, replacing pole top conductor…
BPA proposes to allow T-Mobile to upgrade their wireless network antennas and equipment at four existing sites on BPA transmission structures in Wa…
BPA proposes to allow Verizon to make telecommunications upgrades to its Longacre wireless site located on structure 17/1 of BPA’s Pearl-Keeler No.…
Construct 0.76 mi. of 3-phase line to connect two circuits. Install a 3000kVa transformer to connect two circuits. Convert 1.5 mi. of 1-phase lin…
This project would conduct a study of the current electrical system to identify power poles that are a hazard due to age and wear. Replacements of …
Install and replace a three-phase 75 KVA transformer on Kennedy Rd and Flying Tiger Way. Install and replace a three-phase 75 KVA transformer on Ch…
BPA proposes to allow T-Mobile to upgrade its telecommunications equipment located at structure 2/5 of BPA's Covington-White River Nos. 1 and 2 Tra…
Administration (BPA) proposes to allow AT and T to upgrade its telecommunications equipment at its Redland South wireless site, located on structur…
The Grid Defense Project consists of substation and circuit improvements in Fort Smith, Sebastian County, Arkansas by installing new automation and…
Installation of battery energy storage systems and microgrid switchgear for integration into the SBCC_Hub microgrid.…