Ross-Lexington #1 Meter ProjectCX(s) Applied: B3.1Date: 12/17/2009Location(s): Vancouver, WashingtonOffice(s): Bonneville Power Administration
Office of NEPA Policy and Compliance
December 17, 2009CX(s) Applied: B3.1
Date: 12/17/2009
Location(s): Vancouver, Washington
Office(s): Bonneville Power Administration
Bonneville Power Administration proposes to install meters under the Ross-Lexington #1 transmission line, between tower 1/5 and 1/6, to better understand and predict line sag.