Kerr Tie Line Rebuild
CX(s) Applied: B4.13
Date: 07/30/2015
Location(s): Montana
Offices(s): Bonneville Power Administration

Bonneville Power Administration proposes to rebuild the 400-foot-long Kerr Tie Line that connects BPA's Kerr Substation to Mission Valley Power's (MVP’s) Kerr Substation, and ultimately Northwestern Energy's (NWE’s) Kerr Substation.