Hesperus-Montrose 345 Kilovolt and Curecanti-Lost Canyon 230 Kilovolt Transmission Lines Vegetation Management San Miguel and Dolores Counties CX(s) Applied: B1.3Date: 09/13/2012 Location(s): ColoradoOffices(s): Western Area Power Administration-Rocky ...
Office of NEPA Policy and Compliance
September 13, 2012Hesperus-Montrose 345 Kilovolt and Curecanti-Lost Canyon 230 Kilovolt Transmission Lines Vegetation Management San Miguel and Dolores Counties
CX(s) Applied: B1.3
Date: 09/13/2012
Location(s): Colorado
Offices(s): Western Area Power Administration-Rocky Mountain Region
Western Area Power Administration (Western) would survey for and treat noxious weeds along its right-of-way (ROW) on the Hesperns to Montrose (HS-MTR) transmission lines from structure numbers 126 to 254.