CX-010410: Categorical Exclusion Determination

Oracle to Tucson 115 Kilovolt Transmission Line, Cross Arm Replacements at Structure 2/5 and 7/3 CX(s) Applied: B1.3 Date: 05/02/2013 Location(s): Arizona, Arizona Offices(s): Western Area Power Administration-Desert Southwest Region

Office of NEPA Policy and Compliance

May 2, 2013
Estimated Read Time   min
Oracle to Tucson 115 Kilovolt Transmission Line, Cross Arm Replacements at Structure 2/5 and 7/3
CX(s) Applied: B1.3
Date: 05/02/2013
Location(s): Arizona, Arizona
Offices(s): Western Area Power Administration-Desert Southwest Region

Western Area Power Administration (Western) proposes to conduct cross arm replacements at two wood pole structures located on the existing Oracle to Tucson 115 kilovolt transmission line and Pinal and Pima counties, Arizona.