Install Rip Rap Along Stream Bank at Two Wood Pole Structures Located Along the Bell-Boundary No. 3 Transmission Line CX(s) Applied: B1.3 Date: 03/25/2013 Location(s): Washington Offices(s): Bonneville Power Administration

Office of NEPA Policy and Compliance

March 25, 2013
Estimated Read Time   min
Install Rip Rap Along Stream Bank at Two Wood Pole Structures Located Along the Bell-Boundary No. 3 Transmission Line
CX(s) Applied: B1.3
Date: 03/25/2013
Location(s): Washington
Offices(s): Bonneville Power Administration

Bonneville Power Administration proposes to remove the existing woody debris upstream and downstream at each structure location, place rip rap along the eroded stream bank.