Archer 230 Kilovolt Bay Addition for New Point of Delivery - Stage 07 CX(s) Applied: B4.6 Date: 03/08/2012 Location(s): CX: none Offices(s): Western Area Power Administration-Rocky Mountain Region
Office of NEPA Policy and Compliance
March 8, 2012Archer 230 Kilovolt Bay Addition for New Point of Delivery - Stage 07
CX(s) Applied: B4.6
Date: 03/08/2012
Location(s): CX: none
Offices(s): Western Area Power Administration-Rocky Mountain Region
Tri-State Generation and Transmission Association, Inc. (Tri-State), has requested an interconnection to Western Area Power Administration's (Western) Archer 230/115-Kilovolt (kV) Substation (Archer Substation). The Archer Substation is a Designated Point of Delivery from Western to Tri-State as set forth in Exhibit A of Contract No. 87-LAO-172 (TS-89-0005), Finn Electric Service (Contract).
CX(s) Applied: B4.6
Date: 03/08/2012
Location(s): CX: none
Offices(s): Western Area Power Administration-Rocky Mountain Region
Tri-State Generation and Transmission Association, Inc. (Tri-State), has requested an interconnection to Western Area Power Administration's (Western) Archer 230/115-Kilovolt (kV) Substation (Archer Substation). The Archer Substation is a Designated Point of Delivery from Western to Tri-State as set forth in Exhibit A of Contract No. 87-LAO-172 (TS-89-0005), Finn Electric Service (Contract).