Recovery Act: Colorado State Capitol Building Geothermal Program CX(s) Applied: A9, B2.1, B5.19 Date: 05/15/2012 Location(s): Colorado Offices(s): Golden Field Office
Office of NEPA Policy and Compliance
May 15, 2012Recovery Act: Colorado State Capitol Building Geothermal Program
CX(s) Applied: A9, B2.1, B5.19
Date: 05/15/2012
Location(s): Colorado
Offices(s): Golden Field Office
The Colorado Department of Personnel and Administration (CDPA) would utilize DOE and cost share funds for the construction of an open-loop Ground Source Heat Pump system, including improvements to in-building heating, ventilation and air conditioning systems and development of open-loop production and re-injection wells.
CX(s) Applied: A9, B2.1, B5.19
Date: 05/15/2012
Location(s): Colorado
Offices(s): Golden Field Office
The Colorado Department of Personnel and Administration (CDPA) would utilize DOE and cost share funds for the construction of an open-loop Ground Source Heat Pump system, including improvements to in-building heating, ventilation and air conditioning systems and development of open-loop production and re-injection wells.