Stegall-Gering South Fiber Optic InstallationCX(s) Applied: B4.7Date: 07/14/2011Location(s): Scott's Bluff County, NebraskaOffice(s): Western Area Power Administration-Rocky Mountain Region
Office of NEPA Policy and Compliance
July 14, 2011CX(s) Applied: B4.7
Date: 07/14/2011
Location(s): Scott's Bluff County, Nebraska
Office(s): Western Area Power Administration-Rocky Mountain Region
Western Area Power Administration plans to install a fiber optic line on 15.4 miles of the Stegall-Gering South 115 kilovolt transmission line from the Stegall Substation to the Gering Substation. All work is on existing structures within the existing right of way and will require no road maintenance or reconstruction for access. Western will route the fiber optic line underground from pole 0/1 to the Stegall Substation a distance of approximately 35 feet.