Placer County Biomass Utilization Pilot ProjectCX(s) Applied: A9Date: 05/20/2011Location(s): Placer County, CaliforniaOffice(s): Energy Efficiency and Renewable Energy, Golden Field Office
Office of NEPA Policy and Compliance
May 20, 2011CX(s) Applied: A9
Date: 05/20/2011
Location(s): Placer County, California
Office(s): Energy Efficiency and Renewable Energy, Golden Field Office
The proposed project consists of two stages. Stage 1 would involve analyses, planning, siting, and technology selection activities designed to examine the possibility of the energy facility. Stage 1 is limited to information gathering and dissemination and does not include developing, constructing or operating the 1-3 megawatt (MW) facility. A major part of the Stage 1 activities would include an analysis of the environmental impacts of the facility at the two proposed sites.