L0295 - Saint Johns-Saint Helens Number 1 Interconnection ProjectCX(s) Applied: B4.6Date: 10/15/2010Location(s): Columbia County, OregonOffice(s): Bonneville Power Administration
Office of NEPA Policy and Compliance
October 15, 2010CX(s) Applied: B4.6
Date: 10/15/2010
Location(s): Columbia County, Oregon
Office(s): Bonneville Power Administration
Bonneville Power Administration (BPA) proposes to install a new tap and associated disconnect structures on BPA?s Saint Johns-Saint Helens Number 1 115-kilovolt (kV) transmission line to provide a point of interconnection for Columbia River Public Utility District's (CRPUD's) new Columbia River Substation. CRPUD is constructing the new 115-kV substation in Columbia County, Oregon to serve residential load growth in the area.