Overview

The Hanford Site, a 580-square-mile section of semi-arid desert in southeast Washington, was established in 1943 as part of the Manhattan Project to produce plutonium for national defense. Construction began in October 1943 on the first industrial-scale nuclear reactor, B Reactor, which produced plutonium for the Trinity test and atomic bomb used to help end World War II. During a national security mission that lasted nearly five decades, nine nuclear reactors were built along the banks of the Columbia River to provide materials for five processing facilities that operated
throughout the Cold War era. Hanford produced nearly two-thirds of the plutonium used in the U.S. nuclear weapons stockpile.

With the signing of the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) in 1989 by the DOE, the Washington State Department of Ecology, and the Environmental Protection Agency (EPA), the primary mission of the Hanford Site shifted from national security to environmental cleanup. Hanford’s current mission focuses on preparing to treat millions of gallons of waste in large underground tanks and reducing risks through remediation of contaminated areas, deactivation and decommissioning of facilities, groundwater treatment, and waste management (i.e., waste storage, treatment, and disposal).

Cleanup of the Hanford Site is managed by two DOE offices, the Richland Operations Office (DOE-RL) and the Office of River Protection (DOE-ORP). DOE executes the cleanup and risk-reduction efforts at the site through several prime contractors and their subcontractors. DOE-RL serves as the Hanford Site property owner and oversees cleanup along the Columbia River and in Hanford’s Central Plateau, including groundwater and waste site cleanup, facility cleanout and deactivation and decommissioning, management of solid waste and nuclear materials, and all site support services.

Congress established DOE-ORP in 1998 as a field office to manage the retrieval, treatment, and disposal of approximately 56 million gallons of radioactive tank waste stored in 177 underground tanks in the Central Plateau. The tank waste is material left over from nearly 50 years of plutonium production. In support of this mission, DOE-ORP is responsible for the safe operation of the tank farms and associated 200 Area facilities along with construction and operation of waste transfer systems and treatment facilities, including the Waste Treatment and Immobilization Plant (WTP) located in the Central Plateau.

EM leadership regularly engage a variety of stakeholders and tribal nations regarding the cleanup vision for the Hanford Site. These include regional
elected officials, business leaders, and advisory board members representing more than 30 individual interests and the public at large. Through engagement during development of the Strategic Vision, stakeholders and tribal nations identified several areas in which the Strategic Vision for Hanford could be strengthened, including identifying established dates for noted milestones and completion dates for planned work, as well as goals that could allow quantifiable assessment of results.

A 175-ton crane operated by Hanford Mission Integration Solutions assisted a fellow contractor by lifting equipment onto a platform at Hanford’s Cold Test Facility. The long reach of the crane could complete the job successfully, while team members provided additional safety enhancements, including fall protection and a work deck.
Calendar Year 2020 Accomplishments for Hanford
During low-activity waste vitrification, secondary liquid, called effluent, will be generated from the melter’s off-gas system and when transfer pipes are flushed. These liquids will go to the Effluent Management Facility processing building, where excess water will be evaporated and transferred to Hanford’s nearby Liquid Effluent Retention Facility, and the remaining concentrate will be sent back into the vitrification process.

During low-activity waste vitrification, secondary liquid, called effluent, will be generated from the melter’s off-gas system and when transfer pipes are flushed. These liquids will go to the Effluent Management Facility processing building, where excess water will be evaporated and transferred to Hanford’s nearby Liquid Effluent Retention Facility, and the remaining concentrate will be sent back into the vitrification process.

Planned Cleanup Scope 2021-2031

The coming decade will see the successful launch of one of EM’s largest and most significant cleanup activities — the start of tank waste treatment at Hanford through the DFLAW program. This is a goal EM has been pursuing for more than two decades at Hanford and will address one of the largest environmental challenges in the EM complex.

Tank Waste Treatment

In 2021, commissioning of the DFLAW facilities will occur and DOE will work to complete startup of the WTP LAW Facility, Balance of Facilities, and Analytical Laboratory. Through the DFLAW program, EM anticipates the commencement of low-activity tank waste treatment by the end of 2023. Transitioning these facilities to operational status will commence the treatment of the most mobile form of tank waste, beginning an important new phase of the Hanford Site cleanup effort.

The DFLAW program requires a pretreatment system known as the TSCR system. This system will pretreat tank waste supernate in preparation for waste feed delivery when the WTP LAW Facility is operational. TSCR will be operational by the end of 2021. Waste feed will be staged in the AP Tank Farm until needed for operations. By the end of 2022, upgrades will also be completed at the Liquid Effluent Retention Facility (LERF) and Effluent Treatment Facility (ETF) to support the treatment of the anticipated secondary liquid effluent from DFLAW operations. Additionally, the Integrated Disposal Facility, where the vitrified low-level tank waste will be disposed, will be completed and ready for operations. EM is preparing an analysis of alternatives for high-level waste (HLW) treatment to develop a realistic and achievable path forward for treating the high-level fraction of Hanford’s tank waste.

Risk Reduction

Over the coming decade, the 324 Building will be demolished following the remote excavation of the contaminated soil underneath the facility. Additionally, the 105-K West Fuel Storage Basin will be deactivated and demolished, allowing the K-East and K-West reactors to be placed in interim safe storage. Active groundwater remediation systems will continue operating along the Columbia River and on the Hanford Central Plateau, reducing the risk that contaminated groundwater will leave the site.

DOE will complete the transfer of cesium and strontium capsules, currently at the Waste Encapsulation and Storage Facility, to safer and stable dry storage at a nearby Capsule Storage Area that is currently under construction. Stabilization activities at the Reduction-Oxidation Plant (REDOX), the Plutonium Uranium Extraction Plant (PUREX), and B Plant will place these facilities in a low-risk and low-cost surveillance and maintenance (S&M) configuration. Several high-risk facilities will be demolished, and waste site remediation efforts will continue throughout the Central Plateau with the waste disposed at the Environmental Restoration Disposal Facility. Finally, later in the decade, TRU waste shipments to WIPP are set to resume.

Key Regulatory Milestones 2021-2031*

Cleanup activities at Hanford are governed by the Tri-Party Agreement. Some cleanup activities are also governed by a 2010 Consent Decree between DOE and the State of Washington (as significantly amended by the court in 2016).

  • Complete construction of Effluent Management Facility — December 25, 2020
  • Complete LERF and ETF upgrades to support DFLAW hot commissioning — April 15, 2023
  • Complete LAW Facility hot commissioning and begin production-scale tank waste disposition — December 31, 2023
  • Complete all response actions at 100-K, including placing the last two reactors in interim safe storage — September 30, 2024
  • Transfer cesium/strontium capsules to dry storage — August 31, 2025
  • Complete soil remediation and 324 Building demolition — September 30, 2025
  • Complete single-shell tank retrievals in A/AX Farms — September 30, 2026
  • Remove all mixed waste containers currently located at the Central Waste Storage Complex from outside Storage Areas A and B — September 30, 2026

* Some scheduled milestones have been revised due to COVID restrictions, necessary protocols, and the resulting inefficiencies. DOE will continue to work with regulators to revise milestones, as needed.

Hanford Post 2031 Cleanup Scope

Document Available for Download