February 2018

The Department of Energy’s Voluntary Protection Program Team (Team) recommends that Waste Treatment Completion Company, LLC, complete the 2-year transition process begun in March 2017, after which time the Team will perform a final transitional assessment.

This report summarizes the results of the evaluation of Waste Treatment Completion Company, LLC/Waste Treatment Plant Construction Project conducted February 6-15, 2018, and provides the Associate Under Secretary for Environment, Health, Safety and Security with the necessary information to make the final decision regarding WTCC/WTP’s continued participation as a DOE- VPP “Conditional” Star site.