You are here

EA-1884: Finding of No Significant Impact

Invenergy Interconnection for the Wray Wind Energy Project, Town of Wray, Yuma County, CO

Based on the information contained in the EA, Western's Federal Action would not result in significant environmental impacts.  Western has determined that its action to execute an interconnection agreement to connect the proposed Project to Western's Wray Substation and to take possession of a new switchyard, and either a 4.2-or-0.75-mile double-circuit 115-kV connector line depending on the location of the new switchyard, as well as new interconnection equipment in the existing Wray Substation does not constitute a major Federal action significantly affecting the quality of the human environment within the meaning of NEPA.