CX-010730: Categorical Exclusion Determination

Paisley Geothermal Integration
CX(s) Applied: B1.7
Date: 08/09/2013
Location(s): Oregon
Offices(s): Bonneville Power Administration

Bonneville Power Administration (BPA) proposes to integrate Surprise Valley Electrification Corporation’s (SVEC) 3.65-megawatt Paisley Geothermal Project into BPA’s balancing authority (BA) in response to a SVEC small generator interconnection request. The proposed point of interconnection would be at SVEC’s existing Paisley Substation.