You are here

CX-010723: Categorical Exclusion Determination

Douglas County Public Utility District (PUD) Fiber Land Use Review Request; Case #20130491
CX(s) Applied: B4.9
Date: 08/19/2013
Location(s): Washington
Offices(s): Bonneville Power Administration

Bonneville Power Administration (BPA) proposes to approve a request from the Public Utility District (PUD) to use existing 4-inch conduit and two customer vaults at BPA’s Columbia Substation to install 400 feet of fiber optic cable. The PUD is expanding their fiber system and would like to use existing facilities to the greatest extent possible to minimize disturbance.