  • May 2, 2014

    Final Rule for Amended Energy Conservation Standards for Walk-in Coolers and Walk-in Freezers
    CX(s) Applied: B5.1
    Date: 05/02/2014
    Location(s): CX: none
    Offices(s): Golden Field Office

  • May 2, 2014

    Alfalfa Substation Control House Replacement
    CX(s) Applied: B4.11
    Date: 05/02/2014
    Location(s): Washington
    Offices(s): Bonneville Power Administration

  • May 1, 2014

    Determination of Excess Real Property
    CX(s) Applied: B1.36
    Date: 05/01/2014
    Location(s): Colorado
    Offices(s): Legacy Management

  • May 1, 2014

    Final Rule for New Energy Conservation Standards for Residential Furnace Fans
    CX(s) Applied: B5.1
    Date: 05/01/2014
    Location(s): CX: none
    Offices(s): Golden Field Office

  • May 1, 2014

    Big George-Heart Mountain 69-Kilovolt Transmission Line Glendale Tap Replacement (Amended)
    CX(s) Applied: B4.13
    Date: 05/01/2014
    Location(s): Wyoming
    Offices(s): Western Area Power Administration-Rocky Mountain Region

  • May 1, 2014

    Test Reactor Area (TRA)-640 Fire Sprinkler System Modifications
    CX(s) Applied: B2.5
    Date: 05/01/2014
    Location(s): Idaho
    Offices(s): Nuclear Energy

  • April 30, 2014

    Celilo Converter Station Upgrades (update to previous CX issued on 7/25/13 and 3/11/14)
    CX(s) Applied: B4.11
    Date: 04/30/2014
    Location(s): Oregon
    Offices(s): Bonneville Power Administration

  • April 30, 2014

    Structure and Debris Removal from Howes and Bird's Eye View Properties
    CX(s) Applied: B1.23
    Date: 04/30/2014
    Location(s): Montana
    Offices(s): Bonneville Power Administration

  • April 29, 2014

    Connectivity Between Fractures and Pores in Hydrocarbon-Rich Mudrocks
    CX(s) Applied: A9, B3.6
    Date: 04/29/2014
    Location(s): Texas
    Offices(s): National Energy Technology Laboratory

  • April 29, 2014

    Vapor Space Corrosion Testing of Carbon Steel
    CX(s) Applied: B3.6
    Date: 04/29/2014
    Location(s): South Carolina
    Offices(s): Savannah River Operations Office

  • April 29, 2014

    Subcontractor Repair of Roof Leaks at 717-16K
    CX(s) Applied: B1.3
    Date: 04/29/2014
    Location(s): South Carolina
    Offices(s): Savannah River Operations Office

  • April 29, 2014

    Install One Power Pole and Three Anchors Northwest of 704-1N
    CX(s) Applied: B1.3
    Date: 04/29/2014
    Location(s): South Carolina
    Offices(s): Savannah River Operations Office

  • April 29, 2014

    Archer Substation Microwave Building Fiber Optic Installation
    CX(s) Applied: B4.7
    Date: 04/29/2014
    Location(s): Wyoming
    Offices(s): Western Area Power Administration-Rocky Mountain Region

  • April 29, 2014

    OCGen Module Mooring Project
    CX(s) Applied: B5.25
    Date: 04/29/2014
    Location(s): Maine
    Offices(s): Golden Field Office

  • April 29, 2014

    Keeler and Troutdale Substations Communication Equipment Additions
    CX(s) Applied: B1.7
    Date: 12/30/2013
    Location(s): Oregon, Oregon
    Offices(s): Bonneville Power Administration

  • April 28, 2014

    Recovery Act: Slipstream Testing of a Membrane Carbon Dioxide Capture Process for Existing Coal-Fired Power Plants
    CX(s) Applied: A1, A9, B3.6
    Date: 04/28/2014
    Location(s): CX: none
    Offices(s): National Energy Technology Laboratory

  • April 28, 2014

    Reducing the Impacts of Deterioration of Well Cement Technology
    CX(s) Applied: B3.6
    Date: 04/28/2014
    Location(s): Texas
    Offices(s): National Energy Technology Laboratory

  • April 28, 2014

    2014 Alvey District Wood Pole Replacement Projects
    CX(s) Applied: B1.3
    Date: 04/28/2014
    Location(s): Oregon, Oregon, Oregon
    Offices(s): Bonneville Power Administration

  • April 28, 2014

    2014 Chemawa District Wood Pole Replacement Projects
    CX(s) Applied: B1.3
    Date: 04/28/2014
    Location(s): Oregon, Oregon, Oregon, Oregon, Oregon
    Offices(s): Bonneville Power Administration

  • April 28, 2014

    Non-Newtonian Multiphase Laboratory
    CX(s) Applied: B3.6
    Date: 04/28/2014
    Location(s): West Virginia
    Offices(s): National Energy Technology Laboratory

  • April 28, 2014

    Mixed Waste Management Facility Cap Drainage Repairs
    CX(s) Applied: B6.1
    Date: 04/28/2014
    Location(s): South Carolina
    Offices(s): Savannah River Operations Office

  • April 28, 2014

    A Portable, Two-Stage, Antifouling Hollow Fiber Membrane Nanofiltration Process
    CX(s) Applied: A9, A11, B3.6
    Date: 04/28/2014
    Location(s): New Mexico
    Offices(s): National Energy Technology Laboratory

  • April 28, 2014

    A Portable, Two-Stage, Antifouling Hollow Fiber Membrane Nanofiltration Process
    CX(s) Applied: A9, A11, B3.6
    Date: 04/28/2014
    Location(s): New Mexico
    Offices(s): National Energy Technology Laboratory

  • April 28, 2014

    High Pressure Immersion and Reactive Transport Laboratory
    CX(s) Applied: B3.6
    Date: 04/28/2014
    Location(s): Oregon
    Offices(s): National Energy Technology Laboratory

  • April 28, 2014

    Oxy-Fired Pressurized Fluidized Bed Combustion - Phase II
    CX(s) Applied: A1, A9, B3.6
    Date: 04/28/2014
    Location(s): CX: none
    Offices(s): National Energy Technology Laboratory