Order

DOE O 413.3B

Program and Project Management for the Acquisition of Capital Assets

Nov 2010

Guide

DOE G 413.3-1

Managing Design and Construction Using Systems Engineering

Sep 2008

Guide

DOE G 413.3-2

Quality Assurance Guide for Project Management

Jun 2008

Guide

DOE G 413.3-3

Safeguards and Security for Program and Project Management

Aug 2013

Guide

DOE G 413.3-4A

Technology Readiness Assessment

Sep 2011

Guide

DOE G 413.3-5A

Performance Baseline

Sep 2011

Guide

DOE G 413.3-6A

High Performance Sustainable Building

Nov 2011

Guide

DOE G 413.3-7A

Risk Management

Jan 2011

Guide

DOE G 413.3-8

Environmental Management Cleanup Projects

Cancelled

Guide

DOE G 413.3-9

Project Review Guide for Capital Asset Projects

Sep 2008

Guide

DOE G 413.3-10A

Earned Value Management System (EVMS)

Mar 2012

Guide

DOE G 413.3-11

Project Management Lessons Learned

Cancelled

Guide

DOE G 413.3-12

Project Definition Rating Index (PDRI)

(PDRI Spreadsheet)  

Jul 2010

Guide

DOE G 413.3-13

Acquisition Strategy for Capital Asset Projects

Jul 2008

Guide

DOE G 413.3-14

Information Technology Projects

Cancelled

Guide

DOE G 413.3-15

Project Execution Plans

Sep 2008

Guide

DOE G 413.3-16A

Project Transition/Closeout (CD-4)

Oct 2011

Guide

DOE G 413.3-17

Mission Need Statement

Jun 2008 

Guide

DOE G 413.3-18A

Integrated Project Team Guide for Formation and Implementation

Feb 2012

Guide

DOE G 413.3-19, Chg 1

Staffing Guide for Project Management

(Staffing Model Spreadheet)

Oct 2011

Guide

DOE G 413.3-20

Change Control Management

Jul 2011

Guide

DOE G 413.3-21

Cost Estimating Guide

May 2011

 

Standard Operating Procedures (SOP) and Handbooks

Guidance

Type

Guidance Title and Link

Date Published

SOP

Energy System Acquisition Advisory Board (ESAAB) SOP

Jul 2014

SOP

Earned Value Management System (EVMS) and Project Analysis Standard Operating Procedure (EPASOP)

Mar 2014

SOP

External Independent Review (EIR) SOP

Feb 2014

SOP

Independent Cost Review (ICR) and Independent Cost Estimate (ICE) SOP

Sep 2013

SOP

Earned Value Management System (EVMS) Surveillance SOP

Sep 2013

Handbook

Work Breakdown Structure (WBS) Handbook

Aug 2012

 

Secretarial Memoranda Regarding Project Management

Memorandum Title and Link

Date Published

Improving Project Management

Aug 2005

Integrating Safety into Design and Construction

Dec 2005

Project Management Expectations for Financial Assistance Activities 

Jun 2006

"Paper" Energy Systems Acquisition Advisory Board Process

Jan 2009

Project Full Funding Policy in the Annual Budget Request 

Jan 2009

Management Principles

Dec 2009

Project Management Principles

Mar 2010

Project Assessment and Reporting System (PARS II) 

May 2010 

Project Peer Reviews

Apr 2011

Project Assessment and Reporting System (PARS II) Data Quality

Jun 2012

Aligning Contract Incentives for Capital Asset Projects

Dec 2012

Improving Capital Asset Project Management

Apr 2013

 

Capital Asset Budget Guidance

Title and Link
Non-IT Capital Asset Budget guidance

 

Capital Asset Plans

Title and Link

Date Published

OMB Circular A-11, Part 7,  Planning, Budgeting, Acquisition, and Management of Capital Assets

Current Year

OMB Circular A-11, Appendix K, Selected OMB Guidance and Other References Regarding Capital Assets

Current Year

GAO-09-3SP GAO Cost Estimating and Assessment Guide, Best Practices for Developing and Managing Capital Program Costs

Mar 2009

GAO-12-120G GAO schedule assessment guide - best practices for project schedules (exposure draft)