Savannah River Site Waste Solidification Building Corrective Actions from the January 2013 Report on Construction Quality of Mechanical Systems Installation and Fire Protection Design [HIAR SRS-2013-5-07]

Activity Description/Purpose:

  1. Review the corrective actions being implemented by the construction contractor to address Findings 1-4, 6, and 9 from a construction quality review performed by the Office of Health, Safety and Security (HSS) (Reference 1).
  2. Meet with the SRS WSB project staff and Savannah River Nuclear Solutions (SRNS) engineers to discuss the proposed corrective actions discussed in Reference 2, and clarify additional reviews to be performed by SRNS engineers to ensure the adequacy of the contractor’s corrective actions.