You are here

Independent Oversight Activity Report, Idaho Cleanup Project – November 2013

November 2013

Pre-restart Visit to the Integrated Waste Treatment Unit by the Defense Nuclear Facilities Safety Board [HIAR-ICP-2013-11-19]

This Independent Activity Report documents an oversight activity conducted by the Office of Health, Safety and Security’s (HSS) Office of Safety and Emergency Management Evaluations from November 19-22, 2013, at the Integrated Waste Treatment Unit facility of the Idaho Cleanup Project.  The activity consisted of the HSS Site Lead touring the newly modified IWTU facility to observe the many process and equipment modifications that have been made since the facility was shut down.  In addition, the Site Lead met independently with key operations office staff and observed the Defense Nuclear Facilities Safety Board-led interviews with key operations office, project, and contractor personnel.