Review of Oak Ridge Environmental Management Radiological Controls Activity Level Implementation

The purpose of this set of facility specific Independent Oversight targeted reviews is to evaluate the flowdown of occupational radiation protection requirements, as expressed in facility RPPs, to work planning, control, and execution processes, such as radiological work authorizations, including radiological work permits (RWPs) and other technical work documents (TWDs).