CRAD, Nuclear Facility Construction - Mechanical Equipment - June 26, 2012

June 26, 2012

Nuclear Facility Construction - Mechanical Equipment Installation, (HSS CRAD 45-53, Rev. 0)

The purpose of this criteria review and approach, this CRAD includes mechanical equipment installation, including connections of the equipment to installed piping systems, and attachments of the equipment to structures (concrete, structural steel, or embed plates).  Mechanical equipment includes items such as pumps and motors, valves, tanks, glove boxes, heat exchangers, ion exchangers, service air system, fire pumps and tanks, and heating, ventilation, and air condition (HVAC) equipment such as fans, scrubbers and filters.